FIVE (5) – HOUR BROWN OUT ON TUESDAY, WHOLE OF OLONGAPO CITY
FIVE (5) – HOUR BROWN OUT ON TUESDAY, MAY 15, WHOLE OF OLONGAPO CITY (please click here for full view of notice)
| PUBLIC UTILITIES DEPARTMENT | ||||||
| NOTICE OF POWER INTERRUPTION | ||||||
| DATE | TIME | AFFECTED AREAS/ METERING | Cause of Interruption | REASON (S) | ||
| FROM | TO | |||||
| Tuesday, May 15, 12 | 8:00 AM | 1:00PM | PUD 69kv line, Whole of Olongapo | NGCP | 1 | Replacement of Power fuse assembly of 10 MVA Power Transformer Phase B and C |
| 2 | Hot Spot Connection | |||||
| a. Power fuse terminal connector Phase A | ||||||
| b. D.S. Terminal connection overhead Phase A | ||||||
| c. 560L4 Terminal connector at Pole #3 Phase B, Pole #2 Terminal connector Phase A | ||||||
| 3 | Preventive maintinance Substation Feeder breaker | |||||
| Note : Power will be restored anytime without notice upon completion of works. | ||||||
| Submitted by: | Approved by: | |||||
| RAMON D. BALAGTAS | ENGR. LUISITO M. LOPEZ | |||||
| Head,Technical Division | General Manager | |||||
| Checked by: | ||||||
| ENGR. RAMON C. ZAVALLA | ||||||
| Asst. Gen. Mgr. | ||||||
| OIC, Technical Division | ||||||
|
|
||||||